Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84044 REL 32: 1996-043-00 EXP JCAPE O&M
Project Number:
Title:
Johnson Creek Artificial Propagation Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
84044 REL 32
Contract Title:
1996-043-00 EXP JCAPE O&M
Contract Continuation:
Previous: Next:
84044 REL 2: 1996-043-00 EXP JCAPE O&M
Contract Status:
Issued
Contract Description:
This project is a small-scale supplementation initiative designed to increase the survival of a weak but recoverable spawning aggregate of summer Chinook salmon.  The goal of this project is to prevent the extirpation of the Endangered Species Act (ESA) listed Johnson Creek summer Chinook and begin their recovery through supplementation.  This project is permitted by the NOAA Fisheries to rear up to 150,000 Chinook salmon smolts each year for release into Johnson Creek.

The Johnson Creek Artificial Propagation Enhancement Project (JCAPE) is identified in the 2008 FCRPS Biological Opinion in RPA Hatchery Strategy 2, Action 41 – Implement Safety Net Programs to Preserve Genetic Resources and Reduce Short-term Extinction Risk. Specifically, for Snake River Spring/Summer Chinook.  It is further stated in this RPA to fund the Johnson Creek/South Fork Salmon River safety net supplementation program, as described in the existing Section 10 permit.  This action funds the actual implementation, operation, and monitoring of a safety net project.  The Johnson Creek Artificial Propagation Enhancement project, a safety net project, utilizes existing hatchery facilities (McCall Fish Hatchery) to conduct salmon supplementation release of up to 100,000 smolts per year.  The Johnson Creek Artificial Propagation Enhancement Project is the only Chinook salmon supplementation project in the Salmon River Basin.  The Johnson Creek Artificial Propagation Enhancement Project had been issued an ESA Section 10 permit (Permit number 1250) by NOAA Fisheries to conduct salmon supplementation activities through 2010.  In 2017, the project received ESA permitting through a 4d Rule and Biological Opinion through the HGMP process with NOAA Fisheries.  

This contract will provide funds to:
·        Conduct Salmon Supplementation of the Johnson Creek Summer Chinook Salmon, a safety net program;
·        Provide for administrative oversight of the project; and
·        Share project results through Reports and Presentations

In 2024, installation and operation of a temporary adult Chinook salmon weir and trap will continue with the collection of brood stock for use in the Johnson Creek Artificial Propagation Enhancement Project.  Juvenile salmon (smolts) from the 2022 brood year will be released into Johnson Creek in March or April of 2024.  Juvenile salmon from the 2023 brood year will continue to be reared at the McCall Fish Hatchery.  These fish will be marked with CWT in July 2024.  Specifically, in 2024 the project will:

-         Operate an adult salmon trap on Johnson Creek.
-         Collect and spawn up to 52 pairs of adult salmon.
-         Release 140,000 BY21 smolts back into Johnson Creek.
-         Rear up to 160,000 BY22 juveniles at the McCall Fish Hatchery.
-         Update Annual Operating Plan and submit to NOAA Fisheries prior to adult salmon trapping season.
-         Prepare Brood Year 2022 Report and 2023 Adult Trapping Report.

Since 1998, salmon supplementation has been occurring on Johnson Creek.  This action was taken to begin the recovery of the Johnson Creek spawning aggregate.  The JCAPE project has worked with the Idaho Department of Fish and game (IDFG) and the U.S. Fish and Wildlife Service (USFWS) to rear a limited number of smolts each year at the McCall Fish Hatchery.  The JCAPE project is currently allowed to rear up to 150,000 Johnson Creek smolts to at the McCall Fish Hatchery.  Brood stock has been collected in 1998 and 2000 through 2023.  Smolts from brood stock collection have been released in 2000 and 2002 through 2023.  The JCAPE O&M program is currently rearing fish from brood years from 2022 and 2023.  
Account Type(s):
Expense
Contract Start Date:
01/01/2024
Contract End Date:
12/31/2024
Current Contract Value:
$526,424
Expenditures:
$444,314

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Anthony Broncheau Nez Perce Tribe No Administrative Contact anthonyb@nezperce.org (208) 843-7317
John Gebhards Nez Perce Tribe Yes Contract Manager johng@nezperce.org (208) 634-5290x3305
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Rebecca Johnson Nez Perce Tribe Yes Supervisor beckyj@nezperce.org (208) 621-4629
Scott Kellar Nez Perce Tribe Yes Technical Contact scottk@nezperce.org (208) 827-1669
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Brian McIlraith Bonneville Power Administration Yes Backup COR bjmcilraith@bpa.gov (253) 219-1166
Eric McOmie Bonneville Power Administration Yes COR ermcomie@bpa.gov (503) 230-4964
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023
Craig Rabe Nez Perce Tribe Yes Contract Manager craigr@nezperce.org (208) 634-5290x3311
Carolyn Sharp Bonneville Power Administration No Env. Compliance Lead casharp@bpa.gov (503) 230-5206
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
ESA Compliance Completed B: 165. Produce Environmental Compliance Documentation 12/31/2024
BY 2022 Smolt Rearing and Release C: 176. BY 2022 production activities for the Johnson Creek Supplementation Program 04/21/2024 04/05/2024
BY23 Rearing D: 176. BY 2023 production activities for the Johnson Creek Supplementation Program 12/31/2024
BY 2024 Fish Production E: 176. BY 2024 production activities for the Johnson Creek Supplementation Program 12/31/2024
Nutrient Enhancement F: 44. Nutrient Enhancement in Johnson Creek 09/30/2024 09/10/2024
Maintain Hatchery Facilities G: 61. Hatchery Facilities Maintenance 12/31/2024
Project Information Presentations H: 161. Project Information Presentations 12/31/2024
Outreach and Education I: 99. Conduct outreach and public education efforts 12/31/2024
Project Coordination J: 191. JCAPE O&M Project Coordination 12/31/2024
Update Annual Operating Plan K: 174. Produce Annual Operation Plan and Hatchery Genetic Management Plan 12/31/2024
Completed Annual Report L: 132. Prepare Brood Year 2022 Report (June 2022 to April 2024) 08/01/2024 07/17/2024
Completed Annual Report M: 132. Prepare 2023 Adult Salmon Run Report (June 2023 to December 2023) 09/06/2024 07/17/2024
Effective implementation management and timely contract administration N: 119. Manage and Administer Johnson Creek O&M Project 12/31/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 44 Enhance Nutrients in Water Bodies
  • 3 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Produce Environmental Compliance Documentation
C 176 BY 2022 production activities for the Johnson Creek Supplementation Program 10/26/2023
D 176 BY 2023 production activities for the Johnson Creek Supplementation Program 10/26/2023
E 176 BY 2024 production activities for the Johnson Creek Supplementation Program 10/26/2023
F 44 Nutrient Enhancement in Johnson Creek 10/26/2023
G 61 Hatchery Facilities Maintenance 10/26/2023
H 161 Project Information Presentations
I 99 Conduct outreach and public education efforts
J 191 JCAPE O&M Project Coordination
K 174 Produce Annual Operation Plan and Hatchery Genetic Management Plan 10/26/2023
L 132 Prepare Brood Year 2022 Report (June 2022 to April 2024)
M 132 Prepare 2023 Adult Salmon Run Report (June 2023 to December 2023)
N 119 Manage and Administer Johnson Creek O&M Project